Meeting Minutes

IRC Log of the meeting.

Meeting minutes.

Agenda

20151006 Meeting Agenda



Release Metrics and Incoming Bugs

Release metrics and incoming bug data can be reviewed at the following link:

  • http://kernel.ubuntu.com/reports/kt-meeting.txt



Status: Wily Development Kernel

We are approaching Wily Kernel Freeze this Thurs Oct 8, ~2 days away!
If there are any patches which need to land for 15.10, please get them
submitted immediately. Following the Kernel Freeze deadline, all
patches are subject to our SRU policy and could miss the release.
—–
Important upcoming dates:

  • https://wiki.ubuntu.com/WilyWerewolf/ReleaseSchedule
    Thurs Oct 8 – Kernel Freeze (~2 days away)
    Thurs Oct 15 – Final Freeze (~1 weeks away)
    Thurs Oct 22 – 15.10 Release (~2 weeks away)



Status: CVE’s

The current CVE status can be reviewed at the following link:

  • http://kernel.ubuntu.com/reports/kernel-cves.html



Status: Stable, Security, and Bugfix Kernel Updates – Precise/Trusty/lts-utopic/Vivid

Status for the main kernels, until today:

  • Precise – Kernel Prep
  • Trusty – Kernel Prep
  • lts-Utopic – Kernel Prep
  • Vivid – Kernel Prep

    Current opened tracking bugs details:

  • http://kernel.ubuntu.com/sru/kernel-sru-workflow.html
    For SRUs, SRU report is a good source of information:
  • http://kernel.ubuntu.com/sru/sru-report.html

    Schedule:

    cycle: 27-Sep through 17-Oct
    ====================================================================
    25-Sep Last day for kernel commits for this cycle
    27-Sep – 03-Oct Kernel prep week.
    04-Oct – 10-Oct Bug verification & Regression testing.
    11-Oct – 17-Oct Regression testing & Release to -updates.
    Note: We have gotten off to a late start on this cycle due to some patches
    that came in at the last minute. We intend to stick to the schedule
    though that may change as we get farther along.



Open Discussion or Questions? Raise your hand to be recognized

No open discussion.